0:00 initial setup
6:00 configuration
of “remote start stop” , “control signals” back to the Cloacina system (“motor
running” feedback, and “general tub fail”
alarm for a ‘pump-faulted’ condition)
7:38 “remote start up” setup.
9:27 Setting up
auxiliary relays for control signals.
10:00 (describing ‘manual speed adjust” to adjust the speed
the pump flows at
14:00 - 15:28 This shows you what a regular pump should
look and behave like for an Operator.
15:30 programming 4-20
mA speed control for some sites.
17:55 getting pump
back to “manual speed” from 4-20 mA speed.
19:30 - 20:38 how to
prime pump
20:38 : 21:07 how to place pump back into normal state after
priming.
21:07 physical
electrical connections on the back of the pump