Adjusting the Thermal overload on Seepex WAS pumps
To update the WAS pump
thermal overload, please follow section
4.3 and 5 of the attached manual (also pasted below).
The units being adjusted are inside the panel, typically in
the bottom left, where highlighted in yellow in the screenshot below.
Run the WAS pump for
60 minutes and then set the overload as
per the instructions. (note, check
whether you’re working in C or F so the adjustment can be done correctly; see section 5.3).
Related Articles
Maintenance Series Video: FAS Chamber Design and Pump Pulling
A sample Flygt 3171 O&M manual is attached to this post. DISCLAIMER Cloacina, LLC assumes no liability for the accuracy, completeness, safety or usefulness of any assistance, information, media, apparatus, product or process contained on this website ...
Aerzen Blower Thermal Switch adjustment - Temperature adjustment
The Aerzen Blowers have two thermal switches. One is a direct motor thermocouple which is not adjustable. These are typically set fairly high. The second thermal switch is a thermocouple which is monitoring the internal Blower temperature. This ...
"Fail to run" alarm/alert on a chemical dosing pump
On some Cloacina systems, the PLC determines whether a chemical dosing pump is running by measuring the amperage drawn on the pumps 120V power wiring within the control panel. If the measurement device used to read this amperage is not fully tuned, a ...
Blue-White Peristaltic Pump Setup and Configuration for MEMPAC-R and MEMPAC-M systems
<br> 0:00 initial setup 6:00 configuration of “remote start stop” , “control signals” back to the Cloacina system (“motor running” feedback, and “general tub fail” alarm for a ‘pump-faulted’ condition) 7:38 “remote start up” setup. 9:27 Setting ...
Blue White M4 chemical dosing pump setup, tube replacement, and maintenance
The Blue-White M4 pump is often used for CIP chemicals, as well as pH adjustment, coagulant dosing, and antifoam dosing. FYI tube replacement is shown starting at minute 16. <br>